For more information about using liquidated damages in construction and engineering projects, please contact our dispute resolution solicitors on 01332 226 125 or complete the form below.
Conveyancing
Explore All ConveyancingCriminal Defence
Explore All Criminal DefenceEstate Planning
Explore All Estate PlanningEstate Administraion
Explore All Estate AdministraionDispute Resolution
Explore All Dispute ResolutionFamily & Matrimonial
Explore All Family & MatrimonialMotoring & Driving Offences
Explore All Motoring & Driving OffencesResidential Property
Explore All Residential PropertyResidential Property Disputes
Explore All Residential Property DisputesWills, Trusts & Estate Disputes
Explore All Wills, Trusts & Estate DisputesAgriculture
Explore All AgricultureBusiness Recovery
Explore All Business RecoveryCharities & social enterprises
Explore All Charities & social enterprisesCommercial Disputes
Explore All Commercial DisputesCommercial Law & Contracts
Explore All Commercial Law & ContractsCommercial Property
Explore All Commercial PropertyCorporate & Finance
Explore All Corporate & FinanceData Protection
Explore All Data ProtectionDebt Services
Explore All Debt ServicesEcclesiastical Law
Explore All Ecclesiastical LawEducation Law
Explore All Education LawEmployment Law
Explore All Employment LawFamily Businesses
Explore All Family BusinessesFinance Dispute Resolution
Explore All Finance Dispute ResolutionFinancial & Business Crime
Explore All Financial & Business CrimeInsurance Litigation
Explore All Insurance LitigationIntellectual Property
Explore All Intellectual PropertyLicensing
Explore All LicensingRegulatory & Corporate Defence
Explore All Regulatory & Corporate Defence
Liquidated damages clauses are often found in construction contracts. The amounts to be paid can be significant and it is therefore not surprising that their validity is often disputed by the paying party.
One of the most common grounds for dispute is that the liquidated damages clause is not effective as it amounts to a ‘penalty’.
12 March 2018
Insight
Liquidated damages are pre-agreed amounts of compensation which are to be paid to the ‘innocent’ party to a contract by the ‘contract-breaker’ on the occurrence of specified breaches of contract; liquidated damages are, for example, commonly payable when there is a delay in completing works by the agreed completion date.
Liquidated damages provide certainty and avoid a dispute regarding the amount to be deducted for the breach, as the right to be paid liquidated damages arises automatically upon the specified breach of contract occurs.
If liquidated damages are not agreed in advance then, in the event of a breach of contract, the usual remedy for the innocent party is payment of general damages i.e. an amount of compensation (to be determined by the Court) which is paid to the innocent party by the contract-breaker. In order to be successful in a claim for general damages, the innocent party must be able to prove its loss and that the breach of contract caused that loss. Court proceedings to determine the number of general damages which should be paid can, therefore, be expensive and time-consuming meaning that liquidated damages can often be a much simpler solution.
Care should be taken to ensure that liquidated damages do not amount to a penalty; a penalty is effectively a clause which punishes a party for its breach of contract. Liquidated damages should provide an alternative to the performance of the contractual obligation in question, rather than act as a punishment.
It used to be the case that in order to avoid being a penalty, liquidated damages had to be a ‘genuine pre-estimate of loss’ which would be suffered by the innocent party in the event of the specified breach of contract occurring. The Supreme Court did, however, clarify the law in this area in 2015 when considering the cases of Cavendish Square Holding v El Makdessi; ParkingEye v Beavis. In its judgment, the Supreme Court stated that:
As a result of the Supreme Court’s decision in Cavendish Square Holding v El Makdessi; ParkingEye v Beavis, the fact that a liquidated damages clause may require the contract-breaker to pay more than what would have been a ‘genuine pre-estimate of loss’ does not necessarily mean that it will be construed as a penalty.
The wider interests of the innocent party in the performance of the contract breaker’s primary contractual obligations will also be considered (i.e. so as to establish whether there is commercial justification for enforcing the clause). The commercial bargaining power of the parties at the time the contract was formed will also be taken into account; it seems unlikely that a Court would refuse to enforce a liquidated damages clause in a contract which was negotiated between legally represented parties of equal bargaining power.
Many contractors object to liquidated damages clauses as they cannot see past the principal that it involves them making payment of sums to the employer. However, liquidated damages clauses can be a positive step for a contractor as they act as a limit on the contractor’s liability in the event of the specified default occurring.
By agreeing to a liquidated damages clause contractors know the extent of their liability in the event of the specified default occurring. A well-negotiated liquidated damages figure could result in the contractor saving money when compared to general damages which may be awarded by a court, including the legal costs that the contractor will have needed to spend resolving the dispute.
Many of our clients are now using liquidated damages clauses to their advantage, for example, when trying to stress the importance of meeting completion deadlines to employees and/or subcontractors as there is a figure in black and white for everyone to see the effect on the contractor of the project being delivered late.
For more information about using liquidated damages in construction and engineering projects, please contact our dispute resolution solicitors on 01332 226 125 or complete the form below.
Related Services


The Renters’ Rights Act 2025 reshapes England’s private rental sector, strengthening tenant rights and raising property standards.
Read More

Practical checklist to help landlords and property managers comply with the Renters’ Rights Act 2025 and new tenancy regulations.
Read More

Learn what to do when a commercial lease ends, including renewal rights, risks of staying without a lease, and avoiding disputes.
Read More

Key considerations for tenants before signing a commercial lease, including use, repairs, rent, break clauses, and security of tenure.
Read More

An overview of the searches that should be considered when carrying out commercial property transactions.
Read More

The Energy Performance Certificate (EPC) regime is set to tighten from 2023, bringing a significant and consequential change to owners of commercial properties.
Read More

The Government has now published a policy statement setting out its plans for COVID-19 commercial rent arrears.
Read More

Guidance for landlords and tenants on the key terms to consider when negotiating lease head of terms.
Read More

The economic shock experienced by commercial landlords and tenants during the COVID-19 pandemic has seen the resurgence of turnover rent leases.
Read More

Considerations for landlords and tenants following the new regulations to the use class system introduced earlier this month.
Read More

This article explores some of the most common queries we have received from commercial landlords and tenants since the introduction of the Coronavirus Act…
Read More

The Government announces a package of measures to protect tenants and landlords affected by coronavirus.
Read MoreScroll to next section
Scroll back to the top