In some cases, an employer will want a contractor to start developing designs or to start on site before negotiations have been completed and a formal contract signed.

Parties can start work without the comfort of a full contract and still be protected by using a letter of intent, but what is it and what is the effect of using one?

Benefits of a letter of intent

  • Allows the contractor to start on the design, site or other tasks early, which could result in a reduction of borrowing costs for the employer in the long run.
  • Provides some financial security for the contractor that it will get paid for the work done.
  • Allows the parties to undertake specific works pre-contract without the obligation that the whole works must be completed.

Is a letter of intent binding?

The effectiveness of a letter of intent depends on the form and content. Many people think a letter of intent is just a “statement of intent” but in reality, they often create a contract. Provided that it is drafted correctly, a binding letter of intent (as opposed to a non-binding letter of intent) will be created where there is certainty in the area of offer, acceptance, consideration and intention to create legal relations.

To create a binding letter of intent, you need to consider:

  1. What is the aim of the letter of intent?
  2. What terms and conditions apply to the works referred to in the letter of intent?
  3. What are the requirements for quality and timing of the work?
  4. Is there any insurance that needs to be maintained, such as PI insurance?
  5. Are copyright licences required?
  6. How much needs to be paid; when are the instalments and how to pay (BACS, cheque, etc.)?
  7. How is a dispute going to be resolved (adjudication, arbitration, etc.)?
  8. How are the parties going to end the arrangement?
  9. What happens if a formal contract is entered into?

Is it a “construction contract” under the Construction Act?

Provided that the operation/work that the contractor is conducting is a “construction operation” within section 105 of the Construction Act then the letter of intent will be a qualifying “construction contract”.

This classification will provide additional implied terms such as:

  • Both parties’ ability to refer a dispute to adjudication;
  • The contractor’s entitlement to staged payments (this may have an effect on the payment clause included);
  • The employer’s requirement to serve a pay less notice to withhold payment;
  • The contractor’s right to suspend for non-payment etc.

Expiration of a letter of intent

The parties should ensure that one of the following is achieved:

  • No further work is carried out after expiry; or
  • The expiry date is extended in writing; or
  • The formal contract is signed/executed before expiry.

For support in using letters of intent in construction projects, please contact us on 01332 226 125 or complete the form below.

Scroll to next section

Scroll back to the top

Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.

For more information on how these cookies work, please refer to our Cookies Policy.

Strictly necessary cookies

Necessary cookies enable core functionality such as security, network management, and accessibility. You may disable these by changing your browser settings, but this may affect how the website functions.

Analytics Cookies

These cookies allow us to count visits and traffic sources so we can measure and improve the performance of our website. They help us to know which pages are the most and least popular and see how visitors move around the site. All information these cookies collect is aggregated and therefore anonymous.

Force24 cookies & tracking

This website utilises Force24’s marketing automation platform. Force24 cookies are first-party cookies and are enabled at the point of cookie acceptance on this website. The cookies are named below:

F24_autoID
F24_personID

They allow us to understand our audience engagement thus allowing better optimisation of marketing activity.