Liquidated damages clauses are often found in construction contracts. The amounts to be paid can be significant and it is therefore not surprising that their validity is often disputed by the paying party; one of the most common grounds for dispute is that the liquidated damages clause is not effective as it amounts to a ‘penalty’.
Liquidated damages are pre-agreed amounts of compensation which are to be paid to the ‘innocent’ party to a contract by the ‘contract-breaker’ on the occurrence of specified breaches of contract; liquidated damages are, for example, commonly payable when there is a delay in completing works by the agreed completion date.
Liquidated damages provide certainty and avoid a dispute regarding the amount to be deducted for the breach, as the right to be paid liquidated damages arises automatically upon the specified breach of contract occurs.
If liquidated damages are not agreed in advance then, in the event of a breach of contract, the usual remedy for the innocent party is payment of general damages i.e. an amount of compensation (to be determined by the Court) which is paid to the innocent party by the contract-breaker. In order to be successful in a claim for general damages, the innocent party must be able to prove its loss and that the breach of contract caused that loss. Court proceedings to determine the number of general damages which should be paid can, therefore, be expensive and time-consuming meaning that liquidated damages can often be a much simpler solution.
Care should be taken to ensure that liquidated damages do not amount to a penalty; a penalty is effectively a clause which punishes a party for its breach of contract. Liquidated damages should provide an alternative to the performance of the contractual obligation in question, rather than act as a punishment.
It used to be the case that in order to avoid being a penalty, liquidated damages had to be a ‘genuine pre-estimate of loss’ which would be suffered by the innocent party in the event of the specified breach of contract occurring. The Supreme Court did, however, clarify the law in this area in 2015 when considering the cases of Cavendish Square Holding v El Makdessi; ParkingEye v Beavis. In its judgment, the Supreme Court stated that:
As a result of the Supreme Court’s decision in Cavendish Square Holding v El Makdessi; ParkingEye v Beavis, the fact that a liquidated damages clause may require the contract-breaker to pay more than what would have been a ‘genuine pre-estimate of loss’ does not necessarily mean that it will be construed as a penalty.
The wider interests of the innocent party in the performance of the contract breaker’s primary contractual obligations will also be considered (i.e. so as to establish whether there is commercial justification for enforcing the clause). The commercial bargaining power of the parties at the time the contract was formed will also be taken into account; it seems unlikely that a Court would refuse to enforce a liquidated damages clause in a contract which was negotiated between legally represented parties of equal bargaining power.
Many contractors object to liquidated damages clauses as they cannot see past the principal that it involves them making payment of sums to the employer. However, liquidated damages clauses can be a positive step for a contractor as they act as a limit on the contractor’s liability in the event of the specified default occurring.
By agreeing to a liquidated damages clause contractors know the extent of their liability in the event of the specified default occurring. A well-negotiated liquidated damages figure could result in the contractor saving money when compared to general damages which may be awarded by a court, including the legal costs that the contractor will have needed to spend resolving the dispute.
Many of our clients are now using liquidated damages clauses to their advantage, for example, when trying to stress the importance of meeting completion deadlines to employees and/or subcontractors as there is a figure in black and white for everyone to see the effect on the contractor of the project being delivered late.
To find out how we can support your business in utilising liquidated damages clauses in your project procurement, please contact our Property team on 01332 340 211.
If you have received a letter from our Debt Recovery team, please refer to the contact details provided in the letter to ensure your enquiry is dealt with promptly by the correct member of our team.
For all other enquiries, please complete the form below.
Derby Head Office:
St. Michael’s Court
St. Michael’s Lane
Derby
DE1 3HQ
Tel: 01332 340 211
Fax: 01332 207 601
DX: 729320 Derby 24
SRA number: 509657
Ashbourne:
54, St. John Street
Ashbourne
Derbyshire
DE6 1GH
Tel: 01335 342 208
Fax: 01335 342 010
DX: 26834 Ashbourne
SRA number: 511804
Opening Times:
Our offices are open Monday to
Friday between 08:00 & 18:00